CLAYVILLE PEAKING PLANT

CLAYVILLE PEAKING PLANT

Location: Vineland, NJ

Design Start/Completion: Spring 2014 – Spring 2015

Size & Technology: 64 MW Trent 60 Gas Turbine / Dilution Air SCR / Natural Gas Compression / Utility Sub-Station

In-Service: Spring 2015

Firm Role: Engineering

Waldron was selected as the Engineer of Record for the design of a new peaking facility located adjacent to the Atlantic City Electric Clayville Substation in Vineland, NJ. With the success of the Waldron designed Howard Down Unit #11 project, Vineland Municipal Electric Utility chose to further increase capacity within their service territory.  The option was exercised for the purchase of a second Trent 60, SC and natural gas compressor.  Waldron developed a detailed design package around the Trent 60 engine and substation interconnection.  In addition, Waldron supported VMEU in the selection and oversight of a general contractor to implement our design.  The plant was in-service in the Fall of 2015.